PROFESSION Chartered
Electrical Engineer QUALIFICATIONS ·
B.Sc. (honours) degree
in Electrical Engineering ·
Member of the Institute
of Electrical Engineers (MIEE) ·
Chartered Engineer PERSONAL
DETAILS
SUMMARY OF
EXPERIENCE
·
Proven leadership/management
skills in directing and controlling the work of multi-discipline project
groups, construction and commissioning personnel. ·
Proven track record
of consistently achieving successful completion of projects. ·
Twenty six years experience
of detailed design, specification, procurement, construction and commissioning
of electrical power systems and plant for a wide range of projects in
the oil & gas, chemical process, power generation, transmission
and distribution industries, at voltage levels up to 300kV. ·
Twelve years practical
experience on site in senior roles supervising construction, testing,
commissioning, start-up and handover of project works. ·
Six years specialised
design and construction experience of airport installations. ·
Eight years specialised
experience of railway electrification schemes. ·
Fourteen years experience
of working overseas in Philippines, Malaysia, Spain, North America,
Norway, UAE and Qatar. ·
Fully computer literate
and conversant with all common software applications. CLIENT EXPERIENCE
PIATCO, Dubai Civil
Aviation Authority, London Luton Airport, Statoil, Shell, Dupont, Eastman
Chemical Co., U.K. Ministry of Defence, BOC Cryoplants, Property Services
Agency, Spillers Foods, British Telecom, Imperial College London, Rank
Hovis McDougal, Tyne & Wear Metro, Qatar Ministry of Electricity
& Water, British Rail. EMPLOYMENT HISTORY
Electrical, Communications
& Special Systems Consultant to PIATCO, for the
detailed design and construction phases of a new US$550M, 183,000m2,
13M passenger/year (MPPA) international terminal for Ninoy Aquino International
Airport, Manila. Systems included: electrical, communications, security,
building management, baggage handling, ramp control, airfield lighting,
fuel hydrant, information systems, public address, fire detection, etc.
Ensured
that the EPC contractor’s detailed design was in full accordance with
the conceptual design and specifications inherent in the contract. Subsequently,
that the works were executed in strict accordance with the approved
detailed design, applicable local and international codes & standards
and good workmanship. Finally, witnessed testing and commissioning of
the works in preparation for hand-over and compiled lists of defects
and omissions. Advised the Client on all aspects of the electrical,
communications and special systems works. Demobilised December 2002 upon completion of the works, having
successfully fulfilled consultant’s responsibilities under the contract.
Field
Engineering Manager for the final stages of the construction phase
of a US$540M project comprising the expansion and renovation of the
existing Terminal 1, construction of a new 118,000 m2 satellite
passenger Concourse 1, new domestic passenger Terminal 2, taxiways,
aprons and support facilities including a fuel farm and utility plant. Directed
and coordinated the work of the mechanical and electrical engineering
groups during the final stages of construction & commissioning.
Provided timely engineering support to project managers, supervised
the works of the numerous M&E subcontractors and liaised with the
Client on all M&E engineering matters (10
Engineers reporting).
Demobilised
following successful completion & handover of the works.
Lead Electrical & Special Systems Engineer for the construction phase of a new US$150M Departure Terminal for London Luton Airport to increase passenger
handling capability from 3MPPA to initially 6.3 MPPA and subsequently
to 10 MPPA. Managed
and expedited the work of the site electrical and special systems engineering
teams. Overall responsibility for the installation of electrical power
and special systems including baggage handling, security, airfield lighting,
building management, fire protection, structured cabling, etc. (5 Engineers
reporting). Transferred to another Bechtel project at Dubai International
Airport following successful completion & handover of the works.
Senior Systems Engineer, preparing
special systems specifications and drawings for the conceptual design
of a new international terminal at Ninoy Aquino International Airport.
Systems included: security, building management, terminal management,
baggage handling, flight information display, gate allocation, common
user terminal equipment, airfield lighting, fuel hydrant, & others.
Subsequently, evaluated and reported on contractor’s tenders for the
project works. Demobilised on completion of the conceptual design phase and pending award of the contracts for implementation phases.
Systems Integration
Engineer providing on-site
design services & supervising the installation of the data and communications
network for the new international airport near Kuala Lumpur. Liaised
with other contractors to ensure proper coordination and timely execution
of the installation works. Demobilised following successful completion & handover
of the works.
Supervisory Electrical Engineer
on pre-engineering phase of project to expand Statoil’s Karsto
plant to process rich gas from the North Sea Asgard field. Developed
design of electrical power distribution system with six new substations
and associated 300kV, 66kV, 22kV, 6.6kV, 660V & 400V supplies, plus
modifications and tie-ins to existing equipment. (4 electrical engineers
and 6 designers reporting)
Field Engineering Manager (Electrical & Control Systems)
coordinated work of E&CS Construction
and Engineering Groups throughout the construction phase of the Tetrahydrofuran
(THF) project. Included resolving design problems, controlling changes,
procuring equipment, reporting on progress and costs. (4 Field Supervisors
and E&CS Design Groups reporting) Lead Electrical Engineer on the THF Project. Recruited and established Electrical Group
for new Fluor Daniel office in Northern Spain. Led Group from preliminary
design phase through to design completion on $US200M THF Project. Utilised
integrated CAD and CAM systems, including 3D CAD model, and ‘intelligent’
drawings/data bases. (3 electrical engineers and 8 designers reporting)
Lead Electrical Engineer on
major building services project, directing and controlling the work
of the Electrical Group on site. Also investigated and reported on specialised
motor control and harmonics problems. (3 engineers & 8 designers
reporting)
Project Leader and Superintending
Officer responsible for the
planning, design, specification and contract management of a project
to uprate the power system. Included the construction
of two 3.2MVA 11000/415V substations within the Palace and substantial
HV & LV cable works.
Senior Electrical Engineer preparing specifications, evaluating tenders and vetting schemes
for various power station projects, including building services, telecommunications
and fire protection & detection.
Resident Engineer for
works associated with the expansion and development of Qatar’s 132 &
66 kV transmission system. Overall responsibility on site for the construction
of 15 new substations from original site survey through to satisfactory
completion of the works and handing over to Client, plus extension works
at 10 existing substations.
Area Maintenance Engineer (Transmission):
Directed and controlled maintenance work on BR HV
& LV transmission and distribution cables and associated equipment
in the South Kent area. Overall management of four maintenance depots
with a total staff of 45. Senior Technical Officer (Testing & Commissioning Dept)
Field test engineer required to carry out testing and commissioning
on all electrical substation equipment, including HV & LV switchgear,
transformers, rectifiers, and instrumentation. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||